News

Home >  News

How long to obtain the pressure vessel manufacturing inspection certificates-chinese standard?

Time: 2026-04-09

When customers customize air receiver tank from chinese air tank factory base on chinese pressure vessel manufacturing standards,and need to do authrozied inspeciton on the air tanks, they may wonder how long to obtain the pressure vessel manufacturing inspection certificate.

The final certificate (result) for pressure vessel manufacturing inspection is issued by Chinese Special Equipment Inspection Institutes, the timeframe is as following:

  1. Standard Timeframe (Class II pressure vessels)

No rectification required, first-time pass:

      • Pressure test (H point) completed + final document submission → Inspection certificate issued within 10 working days
      • Some regions/Large equipment: 10-30 working days

General issues:

Manufacturer rectification (usually 7-15 days) → Re-inspection passed → Certificate issued within 7-10 working days

Serious issues:

Rectification + re-inspection + re-audit → 15-30 days + or even longer


  1. Total Process Time (From Inspection Application to Certificate Issuance)

Small Class II Vessels (Standard Air Tanks)

    • Manufacturing cycle: 2-4 weeks
    • Inspection and supervision involved simultaneously, certificate issued within 10 days after manufacturing completion
    • Total cycle: Approximately 3-6 weeks
    • Medium/Customized Pressure Vessels Class II
    • Manufacturing: 1-3 months
    • Inspection and supervision witnessed throughout the process
    • Total cycle: 1.5-3.5 months Months (including documentation and rectification)

  1. Key Factors Affecting Certification Speed

  • 1.Manufacturing Quality: First-pass yield is the fastest; NDT/welding/pressure resistance failures → rework + re-inspection → significant delays
  • 2.Document Completeness: Complete drawings, quality assurance certificate, PQR/WPS, test reports, and test records → faster review
  • 3.Inspection Resources: Special Equipment Inspection Institutes may extend the process by 3-7 days during peak seasons (end of the year/peak season)
  • 4.Expedited Processing: A few institutions can expedite the process by 5-7 days (additional fees)


  1. How to Speed Up the Process
  • 1.Submit complete documentation in advance; review drawings and processes first.
  • 2.Schedule inspections for key processes (welding, NDT, pressure resistance) in advance.
  • 3.Immediately rectify and close any problems found.
  • 4.Submit a complete set of factory documentation on the day of manufacturing completion.

30L以上监检铭牌.png

PREV : None

NEXT : Air receiver tank export packaging

Please leave
message

If you have any suggestions, please contact us

Contact Us
email goToTop